Hone

Lessons · Project management · the budget and the baseline

The budget and the baseline: the yardstick you will be measured against

The cost baseline is the sum of the work-package estimates plus contingency reserve, spread over time; its total is the budget at completion (BAC), and every later cost measurement is taken against it.

Hone is a place to practise a career, one idea a day. This is one of its lessons, written out in full and free to read without an account.

What it is for

Month four, the finance director asks whether the project is over budget. Over which budget? The charter's rough figure, the bottom-up estimate, or the approved baseline? Only the baseline is an answer, because only the baseline was agreed and only the baseline moves through change control.

How to think about it

Roll the work packages up through the WBS to one total. Add the contingency reserve. That is the baseline and its total is BAC. Spread it over the months the work happens in, so that each month has a planned value. Then freeze it; from here it changes only by approved change.

Worked example

1.1 $40,000 + 1.2 $30,000 + 1.3 $50,000 + 1.4 $20,000 = $140,000
The WBS rolled up.
Contingency reserve $10,000
For the risks you identified. Part of the baseline.
BAC = $150,000
Budget at completion. The yardstick.
Spread: months 1 to 5 planned at $20,000, $30,000, $40,000, $40,000, $20,000
Planned value month by month; it is what earned value will be compared to.

Your turn

Write the line that turns the estimates into the baseline.

BAC = work packages +  reserve

The trap

Including the management reserve in the baseline. Management reserve sits above the baseline, for the unknown; the baseline holds the estimates and the contingency for known risks, and performance is measured against that.

Practise the budget and the baseline on HoneA question on it now, a coding challenge where there is one, and it is remembered for review. Free, no email needed.