Hone

Lessons · Project management · planned value, earned value, actual cost

PV, EV and AC: what you planned to have done, what you did, what it cost

Planned value is the budgeted cost of the work scheduled to date; earned value is the budgeted cost of the work actually done; actual cost is what that work really cost.

Hone is a place to practise a career, one idea a day. This is one of its lessons, written out in full and free to read without an account.

What it is for

Spent $100,000 of a $200,000 budget, the team says they are half done. Are they? Only if the work done is worth $100,000 of the plan. Earned value is the number that separates we have spent half from we have done half, and they are different more often than not.

How to think about it

Three questions, in order: by today, what was scheduled to be done, in budget dollars (PV)? What is actually done, in budget dollars (EV)? What has been paid for it (AC)? EV is always measured in the plan's dollars, never in what was spent.

Worked example

BAC = $200,000. By today the plan says 50% should be done
PV = 50% × 200,000 = $100,000. What the plan said would be done, priced at plan rates.
The work done so far is 40% of the scope
EV = 40% × 200,000 = $80,000. What is done, priced at plan rates.
The invoices for that work total $100,000
AC = $100,000. What it actually cost.
Spent half, done 40%, and the plan wanted 50%
Three numbers, one story: behind, and paying more than planned for what is done.

Your turn

BAC is $300,000 and 30% of the work is done. Write the earned value.

EV = 30% ×  = $90,000

The trap

Using actual cost as earned value. Spending $100,000 does not mean $100,000 of work is done; that is the exact mistake earned value exists to catch.

Practise planned value, earned value, actual cost on HoneA question on it now, a coding challenge where there is one, and it is remembered for review. Free, no email needed.