Stakeholders: everyone the project touches, and the few who decide

A stakeholder is anyone who is affected by the project or can affect it; the job is to find them early and know who has the power to decide.

Hone is a place to practise a career, one idea a day. This is one of its lessons, written out in full and free to read without an account.

What it is for

The system launches, and the finance director, who was never asked, refuses to sign off because the reports do not match her month-end. She was a stakeholder from day one; nobody wrote her down. Finding her in week one costs a meeting. Finding her at launch costs the launch.

How to think about it

List everyone who is affected, who pays, who uses the result and who can stop it. Then sort by power and interest: the high-power, high-interest few are managed closely; everyone else is kept informed.

Worked example

Sponsor: pays, can stop it, decides scope
High power, high interest. Manage closely: a short conversation every week.
Warehouse staff: use the result all day
Low power, high interest. Keep informed and listen; they know what will break.
Finance director: signs off the reports
High power, low interest until month-end. Keep satisfied: one review of the report design, early.
Neighbouring team: shares the server
Low power, low interest. Monitor; tell them when the cut-over is.

Your turn

Write the two questions that sort a stakeholder.

How much  do they have, and how much interest?

The trap

Listing only the people who want the project. The ones who can stop it, or who will have to live with it, matter more to the plan than the ones who asked for it.

Practise stakeholders and who decides on HoneA question on it now, a coding challenge where there is one, and it is remembered for review. Free, no email needed.