Lessons · Project management · work packages and their size

A work package: small enough to estimate, big enough to be worth tracking

The lowest box of the WBS is a work package: one deliverable, one owner, an estimate you would sign, and a common rule of thumb of 8 to 80 hours of effort.

Hone is a place to practise a career, one idea a day. This is one of its lessons, written out in full and free to read without an account.

What it is for

A package of 400 hours is reported as in progress for two months, and you find out it is in trouble in month three. A package of 40 hours is done or not done by Friday. The size of the package is the size of the surprise you are willing to accept.

How to think about it

Break a box down until you can say who owns it, how you will know it is done, and what it will cost. If the estimate is a shrug, break it again. If it takes longer to plan the box than to do it, you have gone too far.

Worked example

Box: training delivered, estimated at 320 hours
Too big to see inside. Break it.
Course material written. Trainers briefed. Four sessions of 30 staff run
Three packages: 120 h, 16 h, and 4 sessions × 12 h = 48 h of trainer time.
Each has an owner, a done-test and a cost
Course material: the trainer, done when the sponsor signs the deck, 120 h × $60/h = $7,200.

Your turn

Write the rule of thumb for the size of a work package.

Between 8 and  hours of effort.

The trap

Breaking everything down to the same depth. A well-understood package can stay at 80 hours; a risky one may need to be 8. The rule is about how much surprise you can afford, not about symmetry.

Practise work packages and their size on HoneA question on it now, a coding challenge where there is one, and it is remembered for review. Free, no email needed.